Timetable icon

Timetable

The following dates are subject to change.

2015
  • Notice of Preparation: April 6, 2015
  • 30-day Public Comment Period: April 6 - May 7, 2015
  • Public Meeting: April 14, 2015
2022
  • Notice of Intent: April 15, 2022
  • 30-day Public Comment Period: April 15 - May 20, 2022
  • Public Scoping Meeting: May 5, 2022
2024
  • July 8: Circulation of Draft EIR/EIS
  • August 13: CEQA/NEPA Public Meeting
  • September 26: Virtual Meeting
  • October 9: Comment Period Closes
  • Q3: Project Approval & Final EIR/EIS
2024-2026
  • Design and Permitting Phase
2027-2032
  • Construction begins (3-5 years)

2032
  • New bridge open for the public